Description
Solution
Table of Contents
2.2 Function Analysis in Value Management 5
2.3 ISO 31000 Risk Management Framework. 6
2.4 Literature Review Summary. 7
3.0 Emergent Insights and Knowledge. 7
4.0 Key Learnings and Action Points. 9
1.0 Scope of Inquiry
The hotel project in Riyadh provided an opportunity to evaluate the impact of value engineering (VE) and explore how a more proactive Value Management (VM) approach could have enhanced project outcomes. In the course of the project, VE was applied at RIBA Plan of Work Stage 4, after the design had been finalized and construction was underway. The VE exercise was aimed at identifying cost-saving opportunities without compromising the quality or functionality of the project. The savings were achieved through changes such as alternative fireproof coatings, adjustments to substructure waterproofing materials, and revisions to the mechanical, electrical, and plumbing (MEP) specifications. The cost-saving measures ranged from SAR 13.4 million to SAR 20.4 million, reflecting substantial savings potential as shown in table 1 below.
These are tabled below for consideration by DGCL for further negotiation and agreement with the recommended bidder, or as a post contract variation. No. | ||||
Identified Value Engineering Opportunity | Bidder 1 | Bidder 2 | Bidder 3 | |
1 | Application of cementitious fireproofing coating (to a similar acceptable specification) to columns, beams and trusses in concealed areas. | -469,200.00 | -1,031,931.83 | -2,144,520.00 |
2 | Cold applied bituminous paint of appropriate specification in Substructure waterproofing in lieu of the specified Waterproofing. | -2,289,701.00 | -8,723,090.37 | -11,735,136.44 |
3 | Additional cost for CMU (Concrete Masonry Unit) in lieu of adobe block. | -2,283,762.00 | -710,045.44 | 5,682,515.83 |
4 | Concrete change in mix specifications | -658,753.00 | -1,635,771.62 | -2,400,923.45 |
5 | MEP value engineering proposal schedule | -7,790,455.00 | -8,387,155.15 | -3,017,531.53 |
6 | Roof waterproofing changed to combo roofing system | -444,717.00 | Not Offered | -223,885.62 |
Total (Incl. VAT) | -13,936,588.00 | -20,487,994.41 | -13,839,481.21 |
Table 1: Cost Saving Opportunities
This reactive VE process, however, raises an important question: could these cost-saving opportunities have been identified and implemented more effectively earlier in the project lifecycle? This is the primary focus of my inquiry. By shifting to a Value Management (VM) approach applied at the start of the project, it is possible that a more strategic and value-focused framework for decision-making could have been established. VM that aims at enhancing value by ensuring that objectives are, cost, quality and functionality aligned at an early stage could have offered a more integrated approach with regards to selection and specification standards of materials. Originally VM would have provided a better option of decision making during the conceptual along with the design phases meaning that VE measures would not have to have been so reactive at the subsequent phases.
The inquiry also looks at the disadvantages of the reactive VE which typically happens once there is enough progress to compromise the project schedules, costs, and quality. For instance, the post-bid savings approach in items like fireproof coatings and other waterproofing materials may bring a number of compromises in to the system which in turn can affect the project wrongfully. Due to the need to make decisions and keep within certain budget expectations, these kinds of reactive decisions may call for optimal solutions which are often based on the cost instead of making choices that are best for the project in terms of value for money ad performance over time.
From the literature on VM and risk management, the following implications provide understanding of how such challenges could be tackled at advanced stages of the project life cycle. Had the project considered VM concepts including function analysis, cost consideration, and identification of stakeholders, the project could have concentrated on value optimization, cost, function and performance with minimal compromise on many of the principles. In addition, had the risk management techniques been incorporated within the initial developmental stages, it may have been possible to prevent the emergence of conditions that could lead to cost overruns or unexpected alterations in direction by assessing critical risk factors at an early stage and formulating plans which could reduce the effect of such a factor on the overall development of the project .
The purpose of this report is to investigate how VM at the initial stages might have affected the result identified in the VE exercise and to elaborate the shortcomings of reactive VE and how using proactive approach could eliminate those problems. Thus, answering these questions, the report will give understanding of the further purposes of VM and risk management in relation to project goals and expenditures for its economical usage. The research results could prove useful as a reference in enhancing future project performance, as far as value creation, project cost, and overall success is concerned.
2.0 Literature Review
2.1 Introduction
This literature review elaborates Value Management (VM) and Risk Management frameworks
Related Papers
(Solution) 70S05 Question 3 (AC 3.1) Initial Outline of a Plan for the Effective Induction, Orientation and Socialisation
(Solution) recommendation essential and help Proximie achieve its performance and growth objectives
(Solution) MCIPS Global Strategic Supply Chain Final Project
- Organisation achievement owing to automation of their supply chain, increased confidence and capability, talent management, and employee competency
- Improved stakeholders relations (a later section of stakeholders analysis) easing the change process. Through the iSourcing improvement, WPC would be in a position of harnessing technical and commercial evaluation processes.
- Increased and robust systems and policies which mitigate overall gaps in sourcing system transformation
- Today, only lower than 10% of the entire WPC resources are used to prioritize automation and IT integration successfully. Automation would improve the use of resources in their operations
- Involve their IT and finance departments to ensure within a period of 6 months they
- WPC needs to consider embracing sustainable practices as part of investing in their Industry 4.0 technologies
- Through the adoption of automation, better communication systems backed by AI and ML would be introduced to achieve 70% increased communication effectiveness.
- It is important to increase this through increasing collaboration and alignment of all their interests holistically
- Partnering with institutions for the provision of capacity development opportunities for the PS&M teams and other organizations for the success of the automation process
- Expanding their sourcing of Industry 4.0 technologies. This is to involve highly reputable global companies hence efficient operations and integration of AI
- Source of support from the government to ensure that they are facilitated in terms of policies and appropriate regulations to guide the automation process.
(Solution) CIPS ROSHN Commercial Negotiation Plan-PIN
- This was established after the post-negotiation review which brought out fundamental lessons about the supplier and our company’s negotiation pattern.
- As for certain important aspects, we indeed secured favourable financing conditions; yet, problems arose in attempting to synchronize delivery schedules since such conditions are affected by external supply chain factors.
- The supplier had the better BATNA and acted in a cooperative but very assertive way, and elaborated why the correct approach to negotiations is more equal.
- Further, the experience showed how flexible one has to be, how innovative, and how it pays to be more interested in long-term partnership rather than quick profit. Therefore, it will be useful in the future to improve the techniques of negotiation, improve the knowledge about the actions of suppliers, and improve intercompany and supplier cooperation.
- This will ensure that in future procurement negotiations; better outcomes are achieved.
- ROSHN should ensure that all negotiations within the next 6 months include specific metrics for delivery timelines, quality standards, and service levels, aiming for a 90% satisfaction rate in supplier compliance with these criteria. This approach will help secure more balanced and sustainable agreements.
- Over the next 12 months, ROSHN should develop a supplier relationship management program with bi-annual assessments to track and improve partnership quality. Target at least a 15% increase in supplier engagement scores by the end of the year to gain favorable bargaining positions during market downturns.
- Within 1 month of each major negotiation, conduct debriefing sessions to analyze performance, identify strengths, and address weaknesses. The goal is to improve negotiation effectiveness by at least 10% in the subsequent quarter through targeted adjustments based on these evaluations.
- Within the next 4 months, involve at least 80% of key stakeholders in sourcing strategy meetings to ensure alignment and gather input on critical decisions. This engagement aims to reduce misalignment issues by 20% within the year, resulting in smoother implementation of sourcing strategies.
(Solution) MN7650 MSc Human Resource Management and Training Managing Change and Technology at Work
(Solution) CIPS Assessment 3 PSE Sourcing Essentials
- In summary, sourcing approaches has been evaluated in this assessment. This is through the focus of ADNOC organisation spend category.
- The selected spend category is IT for their advancement of remote and flexible working post-COVID-19 pandemic. Also, by comparing this with other different spend categories, the sourcing approaches evaluated included sole, multiple, single and dual sourcing.
- Through the application of different CIPS tools and techniques Kraljic analysis, Stakeholders analysis, SWOT and PESTLE analysis, a successful evaluation has been put into active process. This is with the best practice in ADNOC being identified and prioritised.
- Further, for the successful sourcing of ADNOC IT system, a successful suppliers appraisal process has been pursued.
- This has been done through the application of Cater’s 10C’s Model. As part of this analysis, the best supplier has been noted and involved.