1.0 Scope of Inquiry
The hotel project in Riyadh provided an opportunity to evaluate the impact of value engineering (VE) and explore how a more proactive Value Management (VM) approach could have enhanced project outcomes. In the course of the project, VE was applied at RIBA Plan of Work Stage 4, after the design had been finalized and construction was underway. The VE exercise was aimed at identifying cost-saving opportunities without compromising the quality or functionality of the project. The savings were achieved through changes such as alternative fireproof coatings, adjustments to substructure waterproofing materials, and revisions to the mechanical, electrical, and plumbing (MEP) specifications. The cost-saving measures ranged from SAR 13.4 million to SAR 20.4 million, reflecting substantial savings potential as shown in table 1 below.
These are tabled below for consideration by DGCL for further negotiation and agreement with the recommended bidder, or as a post contract variation. No. | ||||
Identified Value Engineering Opportunity | Bidder 1 | Bidder 2 | Bidder 3 | |
1 | Application of cementitious fireproofing coating (to a similar acceptable specification) to columns, beams and trusses in concealed areas. | -469,200.00 | -1,031,931.83 | -2,144,520.00 |
2 | Cold applied bituminous paint of appropriate specification in Substructure waterproofing in lieu of the specified Waterproofing. | -2,289,701.00 | -8,723,090.37 | -11,735,136.44 |
3 | Additional cost for CMU (Concrete Masonry Unit) in lieu of adobe block. | -2,283,762.00 | -710,045.44 | 5,682,515.83 |
4 | Concrete change in mix specifications | -658,753.00 | -1,635,771.62 | -2,400,923.45 |
5 | MEP value engineering proposal schedule | -7,790,455.00 | -8,387,155.15 | -3,017,531.53 |
6 | Roof waterproofing changed to combo roofing system | -444,717.00 | Not Offered | -223,885.62 |
Total (Incl. VAT) | -13,936,588.00 | -20,487,994.41 | -13,839,481.21 |
Table 1: Cost Saving Opportunities
This reactive VE process, however, raises an important question: could these cost-saving opportunities have been identified and implemented more effectively earlier in the project lifecycle? This is the primary focus of my inquiry. By shifting to a Value Management (VM) approach applied at the start of the project, it is possible that a more strategic and value-focused framework for decision-making could have been established. VM that aims at enhancing value by ensuring that objectives are, cost, quality and functionality aligned at an early stage could have offered a more integrated approach with regards to selection and specification standards of materials. Originally VM would have provided a better option of decision making during the conceptual along with the design phases meaning that VE measures would not have to have been so reactive at the subsequent phases.
The inquiry also looks at the disadvantages of the reactive VE which typically happens once there is enough progress to compromise the project schedules, costs, and quality. For instance, the post-bid savings approach in items like fireproof coatings and other waterproofing materials may bring a number of compromises in to the system which in turn can affect the project wrongfully. Due to the need to make decisions and keep within certain budget expectations, these kinds of reactive decisions may call for optimal solutions which are often based on the cost instead of making choices that are best for the project in terms of value for money ad performance over time.
From the literature on VM and risk management, the following implications provide understanding of how such challenges could be tackled at advanced stages of the project life cycle. Had the project considered VM concepts including function analysis, cost consideration, and identification of stakeholders, the project could have concentrated on value optimization, cost, function and performance with minimal compromise on many of the principles. In addition, had the risk management techniques been incorporated within the initial developmental stages, it may have been possible to prevent the emergence of conditions that could lead to cost overruns or unexpected alterations in direction by assessing critical risk factors at an early stage and formulating plans which could reduce the effect of such a factor on the overall development of the project .
The purpose of this report is to investigate how VM at the initial stages might have affected the result identified in the VE exercise and to elaborate the shortcomings of reactive VE and how using proactive approach could eliminate those problems. Thus, answering these questions, the report will give understanding of the further purposes of VM and risk management in relation to project goals and expenditures for its economical usage. The research results could prove useful as a reference in enhancing future project performance, as far as value creation, project cost, and overall success is concerned.
2.0 Literature Review
2.1 Introduction
This literature review elaborates Value Management (VM) and Risk Management frameworks
Related Papers
(Solution) CIPD 7C004 Task 2.1 Differences of Primary and Secondary Data
(Solution) (AC4.1) Assess suitable types of contractual arrangements dependent on specific workforce need
Solution Permanent, full-time contracts Permanent, full-time contracts for delivery drivers offer both benefits and drawbacks, making their suitability dependent on ParcelCare’s operational needs and goals. Pros Permanent, full-time contracts provide job security and consistent income for delivery drivers, enhancing employee satisfaction and loyalty. This stability can lead to higher motivation and productivity, reducing turnover rates and the associated costs of recruitment and training as evidenced by Personio (2023). Full-time contracts also facilitate better workforce planning, ensuring ParcelCare has reliable staffing to meet delivery demands. Cons However, these contracts can be less flexible and more costly for the company. Full-time employees typically require benefits such as health insurance, paid leave, and retirement plans, increasing operational expenses. Additionally, the rigidity of permanent contracts may not align with fluctuating delivery volumes, leading to inefficiencies during low-demand periods. Suitability For ParcelCare, full-time contracts can be suitable if delivery volumes are consistently high, ensuring a stable workforce. However, a mixed model that includes part-time or flexible contracts might offer the necessary flexibility to adapt to changing demands while controlling costs. Part-Time Contracts Part-time contracts offer flexibility for delivery drivers, allowing them to balance work with other commitments. Drivers benefit from a stable income, albeit at reduced hours, while ParcelCare can adjust staffing levels according to demand. A significant advantage of part-time contracts is reduced costs associated with employee benefits, as part-time workers may not qualify for full benefits packages (Abogados, 2019). However, part-time drivers may lack the same commitment or availability as full-time employees, potentially impacting reliability and consistency. Zero-Hours Contracts Zero-hours contracts provide maximum flexibility, allowing ParcelCare to scale staffing up or down based on delivery demand without a fixed commitment to provide hours (CIPD, 2023c). For drivers, these contracts offer freedom to accept or decline work, appealing to those seeking flexibility. However, they also result in income uncertainty and lack of guaranteed hours, which can be challenging for drivers seeking stability. For ParcelCare, zero-hours contracts minimise costs during low-demand periods but may lead to difficulties in maintaining a loyal and consistent workforce due to potential driver dissatisfaction. Part-time contracts are most suitable for ParcelCare’s delivery drivers. They offer a stable income and consistent work schedule, which can enhance job satisfaction and reliability while allowing ParcelCare to adjust staffing levels as needed. This balance supports both operational needs and employee stability. Please click the following icon to access this assessment in full