Description
Solution
Table of Contents
2.2 Function Analysis in Value Management 5
2.3 ISO 31000 Risk Management Framework. 6
2.4 Literature Review Summary. 7
3.0 Emergent Insights and Knowledge. 7
4.0 Key Learnings and Action Points. 9
1.0 Scope of Inquiry
The hotel project in Riyadh provided an opportunity to evaluate the impact of value engineering (VE) and explore how a more proactive Value Management (VM) approach could have enhanced project outcomes. In the course of the project, VE was applied at RIBA Plan of Work Stage 4, after the design had been finalized and construction was underway. The VE exercise was aimed at identifying cost-saving opportunities without compromising the quality or functionality of the project. The savings were achieved through changes such as alternative fireproof coatings, adjustments to substructure waterproofing materials, and revisions to the mechanical, electrical, and plumbing (MEP) specifications. The cost-saving measures ranged from SAR 13.4 million to SAR 20.4 million, reflecting substantial savings potential as shown in table 1 below.
These are tabled below for consideration by DGCL for further negotiation and agreement with the recommended bidder, or as a post contract variation. No. | ||||
Identified Value Engineering Opportunity | Bidder 1 | Bidder 2 | Bidder 3 | |
1 | Application of cementitious fireproofing coating (to a similar acceptable specification) to columns, beams and trusses in concealed areas. | -469,200.00 | -1,031,931.83 | -2,144,520.00 |
2 | Cold applied bituminous paint of appropriate specification in Substructure waterproofing in lieu of the specified Waterproofing. | -2,289,701.00 | -8,723,090.37 | -11,735,136.44 |
3 | Additional cost for CMU (Concrete Masonry Unit) in lieu of adobe block. | -2,283,762.00 | -710,045.44 | 5,682,515.83 |
4 | Concrete change in mix specifications | -658,753.00 | -1,635,771.62 | -2,400,923.45 |
5 | MEP value engineering proposal schedule | -7,790,455.00 | -8,387,155.15 | -3,017,531.53 |
6 | Roof waterproofing changed to combo roofing system | -444,717.00 | Not Offered | -223,885.62 |
Total (Incl. VAT) | -13,936,588.00 | -20,487,994.41 | -13,839,481.21 |
Table 1: Cost Saving Opportunities
This reactive VE process, however, raises an important question: could these cost-saving opportunities have been identified and implemented more effectively earlier in the project lifecycle? This is the primary focus of my inquiry. By shifting to a Value Management (VM) approach applied at the start of the project, it is possible that a more strategic and value-focused framework for decision-making could have been established. VM that aims at enhancing value by ensuring that objectives are, cost, quality and functionality aligned at an early stage could have offered a more integrated approach with regards to selection and specification standards of materials. Originally VM would have provided a better option of decision making during the conceptual along with the design phases meaning that VE measures would not have to have been so reactive at the subsequent phases.
The inquiry also looks at the disadvantages of the reactive VE which typically happens once there is enough progress to compromise the project schedules, costs, and quality. For instance, the post-bid savings approach in items like fireproof coatings and other waterproofing materials may bring a number of compromises in to the system which in turn can affect the project wrongfully. Due to the need to make decisions and keep within certain budget expectations, these kinds of reactive decisions may call for optimal solutions which are often based on the cost instead of making choices that are best for the project in terms of value for money ad performance over time.
From the literature on VM and risk management, the following implications provide understanding of how such challenges could be tackled at advanced stages of the project life cycle. Had the project considered VM concepts including function analysis, cost consideration, and identification of stakeholders, the project could have concentrated on value optimization, cost, function and performance with minimal compromise on many of the principles. In addition, had the risk management techniques been incorporated within the initial developmental stages, it may have been possible to prevent the emergence of conditions that could lead to cost overruns or unexpected alterations in direction by assessing critical risk factors at an early stage and formulating plans which could reduce the effect of such a factor on the overall development of the project .
The purpose of this report is to investigate how VM at the initial stages might have affected the result identified in the VE exercise and to elaborate the shortcomings of reactive VE and how using proactive approach could eliminate those problems. Thus, answering these questions, the report will give understanding of the further purposes of VM and risk management in relation to project goals and expenditures for its economical usage. The research results could prove useful as a reference in enhancing future project performance, as far as value creation, project cost, and overall success is concerned.
2.0 Literature Review
2.1 Introduction
This literature review elaborates Value Management (VM) and Risk Management frameworks
Related Papers
(Solution) CIPS ADNOC Onshore Module: Sourcing Essentials in Procurement & Supply
- For logging services, a unique sourcing approach would be used different from other sourcing approaches
- The sourcing appraisal can be expanded to include more factors
- Policies and practices need to be put in place for improving sourcing process
- An improved stakeholders relations and inclusion in sourcing approach selection need to be enhanced
- PS&M team increased awareness for various sourcing approaches and using RFP, RFQ and Product Lifecycle
(Solution) 7C003 Discuss how business acumen can deliver commercial benefits and manage resilience
(Solution) CIPS Royal Commission of AluLa Developing Contracts in Procurement and Supply (PDC)
(Solution) CIPS ADNOC APGCM Module: Contract & Category Management in P&S
- Implement one AI-driven analytics platform by Q4 2024, integrating with existing systems and training staff to enhance forecasting accuracy and negotiate a 10% reduction in supplier costs, led by the IT, procurement, and finance departments. Despite potential initial costs and staff adaptation challenges, this initiative aims to achieve a 15% increase in forecasting accuracy.
- Fully deploy advanced supply chain management software by Q2 2025, partnering with a leading provider and training teams to reduce disruptions by 20%, thus increasing overall supply chain efficiency by 5%. This effort involves collaboration between supply chain management, IT, and vendor management teams, despite initial disruptions and high upfront costs.
- Establish a cross-functional compliance team by Q3 2024 to develop three new policies annually, ensuring 100% compliance with regulations and enhancing reputation metrics by 15%. Led by legal, compliance, and HR departments, this initiative aims to overcome resistance to policy changes and resource-intensive monitoring efforts.
- Implement three financial instruments (futures, options, currency swaps) by Q3 2024, collaborating with financial experts to reduce financial risks by 20% and achieve a 10% increase in financial stability. This effort, led by finance, risk management, and external advisors, addresses potential challenges in market volatility and regulatory constraints.
- Engage multiple suppliers and form five strategic partnerships by Q4 2024, increasing supplier diversity by 30% and improving supply chain reliability metrics by 10%. Led by procurement, vendor management, and supply chain analysts, this initiative aims to mitigate dependency risks and manage supplier relationships effectively. Potential challenges include maintaining consistency in product/service quality across diverse suppliers and increased administrative burden in managing multiple partnerships.
- Conduct market and competitor analyses twice a year starting Q3 2024, aiming to increase procurement cost savings by 15% through better negotiation strategies and timely market insights. This effort, involving procurement, and strategy departments, addresses challenges in data availability and competitive analysis capabilities. Potential challenges include delays in obtaining and analysing market data and difficulty in predicting competitive moves accurately.