Solution
2.0 Analysis of Sourcing Approaches
2.1 Multiple Sourcing
This can be defined as a strategy involved in an organisation prioritising on sourcing of goods and service from wide range of vendors (CIPS, 2023). Multiple suppliers are engaged for one or same products/services. Considering Design Building spend category, multiple sourcing is used. In line with Commercial Team, the amount of spend in this category is SAR350 Million with the budget being annually. The sub-categories of the spend informing need for multiple sourcing is illustrated in the following;
Table 1:Design Building Sub-Categories
Source: Summarised from ROSHN internal documents
Design Building Spend Category | Explanation | Suppliers engaged | Amount of spend (SAR Millions) |
Schematic design | Initial groundwork, research and analysis and programming | BIM Modelling consultancy, Sudasi Studios, Alpha Premium Ltd and Flatworld Solutions | 50 |
Detailed design | Initial engineering, structure, plumbing and electricals | Saudi design group, Omrania, Dun & Bradstreet, Arabian consulting engineering center and Lusha | 200 |
Construction Documentation | Multiple drawings including those for approvals | Saudi design group, Omrania, Dun & Bradstreet, Alpha Premium Ltd and Flatworld Solutions | 100 |
Bidding and construction administration | Reviewing of schematic deign, deign development and construction drawings | BIM Modelling consultancy, Sudasi Studios, Alpha Premium Ltd and Flatworld Solutions | 150 |
To summarise table 1 content, it is clear that the different spend categories in design building is categorised into different areas. In the identified areas, multiple suppliers can be engaged with budgets being varying. The importance of involving the multiple suppliers is for gaining value for money outcomes and achieve standard specifications (Yoon et al., 2020). Apart from the ISO 9001 certification, design building must equally meet the requirements of the municipalities in KSA mandated in designing, spearheading construction process, demolitions and assets alterations. An example of a recent project by ROSHN is the construction of 450,000 square meters project in Southwest Riyad. In design building, the involvement of the multiple sourcing was informed by the following factors;
Table 2:Multiple suppliers in a ROSHN Project
Source: ROSHN Internal documents
In the ROSHN stadium construction project, the multiple suppliers would be the most appropriate in Design Building category. Part of the supplier list framework agreements by the vendor management teams in ROSHN, it detail on evaluation criteria used, life costing, cost-benefit analysis, risks analysis and managing contracts (CIPS, 2023a). The different suppliers are therefore identified. There is nevertheless a need for providing PS&M with opportunities for capacity development for understanding their roles in multiple sourcing. This is since early in 2021, ROSHN was fined by Federal Government of KSA for cancelling a contract after PS&M wrongfully identified the quality expectation as being below standards set.
The advantage of multiple sourcing include existence of multiple suppliers hence a broad choice. For instance, in 2019, ROSHN was engaged in construction of King Salman Park (Saudi Vision 2030, 2024). The outcome of this was engaging different suppliers mandated with ensuring availability of cultural events area (20%), artistic and recreational activities (15%) and relaxing environment (65%). As a result, many suppliers were involved hence increased quality of the project final results as set. Also, the organisation was able to leverage on competitive advantage, hence getting good offer.
The disadvantages include lacking good technologies hence failing in managing documentation and information for multiple sourcing. This can be improved in ROSHN by increasingly investing in technologies for sourcing process. Also, multiple sourcing is time intensive to identify all the suppliers and narrow down to some. In ROSHN, past projects including Sports Boulevard, Green Riyadh and Riyadh Art averaged at 60days in entire process of identifying the multiple suppliers.
The available opportunity for engaging multiple sourcing is informed by need to diversify existing suppliers both locally and internationally (Sim & Kim, 2021). This is the case in ROSHN having based their operations in North and SouthEast of KSA, they are in a position of attracting highly qualified suppliers in the region and beyond hence successful operations.
2.2 Single Sourcing
This is defined as a strategy where a specific supplier is opted for by the buyer even when there exist other potential suppliers (CIPS, 2024a). For example, in ROSHN, in a project such as Qiddiya Entertainment City, a local organisation which is El-Seif Engineering Contracting was sourced for the completion of the project, The rationale of selection of the local firm include the following;
Please click the following icon to access this project in full
Related Papers
(Solution) CIPD Avado AC 4.1 (Email 8) Explain the major statutory rights in leave and working time
(Solution) New CIPD 5HR03: Reward for Performance and Contribution
(Solution) CIPS PIN Final Assessment Negotiation in procurement and supply
- In this integrative assessment for Corporate Award Program establishes it has provided a formal commercial negotiation for Occidental of Oman operating in oil and gas industry.
- Commercial negotiation plan has been developed by reference to data, factual information and CIPS tools. HSE and chemicals portfolio spend category has been identified and evaluated in-depth to come up with an appropriate negotiation plan.
- The importance of identifying the HSE and Chemicals are informed by the previous COVID-19 pandemic which has informed on the need for adopting healthy business environment which is free from any infections.
- Further, coming from the pandemic where the level of business operations had significantly reduced and the organisation need to restart their operations by cleansing their systems and machines. In this case, the need for HSE and the chemicals portfolio in Occidental of Oman has been in an upward trajectory.
- For negotiation successful implementation, Occidental of Oman involves professionals, terms and conditions initiated, holistic readiness and streamlined procurement and supply chain approaches. This is with good forecast and plans being core for guaranteeing customers services delivery on time.
- From the analysis, different tools including SWOT, PESTLE and 4R’s have evidenced that Occidental of Oman is always on the advantage of ensuring they achieve the Best Alternative for Negotiated Agreement (BATNA).
- Also, this report highlight the need for holistic planning by prioritising on all expectation from the initial opening to the closure and agreement phases of negotiation.